December 2026

Anticipated Completion of 69kV Subtransmission Lines

Between mid 2021 and late 2026, the 69kV subtransmission line segments between Riverside's Energy Resource Center (RERC) and both Harvey Lynn Substation and Freeman Substation will be constructed. More information on these project segments can be found here.

March 2025

RPU Wilderness / SCE Wildlife Substation Site Preparation

November 30 2028

RPU System Improvements & Substation Upgrades

November 01 2028

230kV Underground Transmission Line Construction Completion

December 22 2028

230kV Overhead Transmission Line Construction Completion

December 21 2029

RPU Wilderness Substation & Integration Construction Completion

November 01 2029

SCE Wildlife Substation Construction Completion