Project Timeline Update
The Galveston County Consolidated Drainage District is pleased to report significant progress on the Frenchmen’s Creek Flood Mitigation Project in Friendswood.
January 2025: Completion of final design and permitting phases.
February 2025: Acquisition and demolition of five flood-prone residential structures finalized.
March 2025: Site preparation and initial grading began to restore natural floodplain function.
April 2025: Environmental restoration underway, including native vegetation planting and habitat enhancement.
May 2025 (Upcoming): Installation of drainage infrastructure improvements to support floodwater flow.
June 2025 (Projected): Project completion with dedicated greenspace opening to the public.
This project aims to reduce flood risk, improve community safety, and restore natural habitats along Frenchmen’s Creek. GCCDD thanks the community for their support and cooperation throughout the process.
For weekly updates and more information, visit www.gccdd.dst.tx.us/projects.