March 2025

Contract signature with Cadence

Alto and Cadence, the chosen developer, have reached a key milestone with a signed contract, advancing the High-Speed Rail Network between Toronto and Québec City. This marks the start of the crucial design and development phase for the ambitious project, first announced by the Government of Canada on February 19, 2025, and a major step in enhancing national mobility.

February 2025

Government Announcement - Cadence is selected

The Government of Canada announced Cadence as the selected consortium that will work with Alto to develop the Toronto–Québec City high-speed rail project, confirming funding for this phase. This marks a key milestone for the country's largest infrastructure project.  To consult the Government press release.

September 2024

Support from key stakeholders along the corridor

The response from stakeholders has been building steadily. Over the course of the past months, key organizations along the Corridor have publicly communicated their call to action for this project, including: Canadian Chamber of Commerce, Consider Canada, Ontario Chamber of Commerce, Tourism Industry Association of Ontario, Alliance touristique du Québec, Ottawa Board of Trade, The Chamber of Commerce of Metropolitan Montréal, Chambre de commerce et d’industrie de Québec, Chambre de commerce et d’industrie de Trois-Rivières.

July 2024

Proposals Submission by 3 bidding teams

Three consortia pre-qualified in the fall of 2023 (bidding teams) submitted their proposals. The next phase involves evaluating the submission to select the Private Developer Partner who will collaborate with Alto throughout the entire project.

June 2024

Field study workshops with Ontario Indigenous Nations

In June, Alto planned to host collaborative planning workshops for the 2024 field study program with Ontario Indigenous Nations.  

March 19 2024

Martin Imbleau - Intervention at the CCIQ

Alto CEO Martin Imbleau shared the vision for the Québec City–Toronto rapid passenger rail project with the Chambre de commerce et d'industrie de Québec (CCIQ).

April 2024

Launch of the 2024 Field Study program

The 2024 Field Study program, launched in April, runs through December, examining air quality, wildlife, noise, and water. These studies provide key data to guide project decisions and protection measures. Alto also engaged Indigenous Peoples, whose insights are vital to shaping project plans.

February 20 2024

Martin Imbleau - Intervention at the CCMM

Alto CEO Martin Imbleau presented the evolving Québec City–Toronto rapid rail project to the Chamber of Commerce of Metropolitan Montréal (CCMM), now backed by a new federal Crown corporation. Introductory meetings between Indigenous Nations and bidders occurred from February 19 to 27 in Montréal, Ottawa, and Toronto.  

December 05 → December 06 2023

Field study workshops with Quebec Indigenous Nations

Alto hosted collaborative planning workshops for the 2024 Field Study program with Québec Indigenous Nations. These workshops took place in Montréal, Québec.

November 2023

Meetings with key stakeholders along the corridor

In November, Alto CEO Martin Imbleau highlighted the transformative impact of the Toronto–Québec City rail project. He presented its benefits at the Mayor’s Breakfast in Peterborough, the Rail Symposium on Safety & Climate Resiliency, and the NRD23 conference. Imbleau also met with Perrin Beatty, CEO of the Canadian Chamber of Commerce, to discuss the project's role in boosting transportation and economic growth.

October 13 2023

Launch of the RFP process

The Government of Canada issued a Request for Proposals (RFP) to select a private sector partner to refine the Alto project before making a final investment decision.

July 31 2023

Appointment of Martin Imbleau as CEO

The Board of Directors announced Martin Imbleau as the new CEO. After a global search, he officially assumed the role on September 8.

April 2023

Launch of Field studies 2023

Between April and November, Alto planners conducted a series of preliminary field studies for the project, including studies on noise and vibration, fish and fish habitat, wildlife tracking, air quality and water.

March 30 2023

Rob Pritchard speech at Toronto Region Board of Trade's Transportation Symposium

Alto’s Chair, Rob Prichard, addressed the Toronto Region Board of Trade’s Transportation Symposium, highlighting the project's vision, necessity, and upcoming developments.  

March 09 2022

Launch for a Request of Expressions of Interest

In December, the Minister of Transport established VIA HFR, a VIA Rail subsidiary, to advance High Frequency Rail, appointing three board members. Earlier in the fall, Alto expanded its expertise by appointing three professionals for project planning. 

On March 9, the Government of Canada launched the Request for Expressions of Interest (RFEOI) to support Alto’s multi-year procurement process, seeking private sector input on its design, construction, financing, and operation. Responses were submitted by May 31, informing next steps in procurement following an October 31 market update. 

In 2022, Alto conducted further field studies on environmental factors, including noise, air quality, water, and wildlife tracking. 

February 17 2023

Launch of the RFQ by the government

The Government of Canada launched a Request for Qualifications (RFQ), closing on April 24, 2023. By July 20, three bidding teams were selected to compete for a partnership to refine the project in 2024.  Learn More,

On February 23, Alto met with Mayors Shawn Pankow (Smiths Falls) and Genevieve Lajoie (Casselman) to share updates on the Toronto–Québec City rail project, designed to offer fast, frequent, and reliable service connecting communities.

July 06 2021

Procurement preparations

The Government of Canada announced the first steps in preparing for the procurement process to build a new train service from Toronto to Québec City. 

These steps included: 

  • Engaging Indigenous Peoples and communities to obtain feedback on the project. 
  • Engaging with the private sector to determine capacity and seek perspectives on the best possible delivery model. The Government of Canada plans to finalize the delivery model and launch the process to select a private partner. 
  • Accelerating dialogue with partner railways to negotiate dedicated routes and, where necessary, shared access in and out of city centres.
April 2019 → April 2020

Preliminary Field studies

In 2020, Alto planners conducted the first series of preliminary field studies for the project, including studies on noise and vibration, fish and fish habitat, wildlife tracking, air quality and water.

In 2019, the Government of Canada granted funding for and established a Joint Project Office (JPO) as a joint venture between the Canada Infrastructure Bank (CIB) and VIA Rail to conduct de-risking, due diligence, pre-procurement and planning activities; to explore and analyze operating models; and to develop evidence-based options of procurement and financing for the Alto project. The JPO oversaw the Alto project through to the end of 2021.

January 2016

VIA Rail initiates the project

VIA Rail put forward the concept of the construction of Alto between Toronto, Ottawa, Montréal and Québec City.