The City of North Port celebrated a groundbreaking ceremony in March 2023 to kick off the widening of Price Boulevard, a much-anticipated project that will ease congestion on this key roadway and make it more resilient in the event of future storms.

Key Features

  • Four travel lanes/two in each direction
  • A continuous bi-directional center left lane
  • A ten feet wide multi-use path on each side of the roadway

Project Features

By the Numbers:

  • Price Boulevard widening from two lanes to four lanes between Toledo Blade and Sumter boulevards
  • The project is approximately 2.8 miles in length
  • New traffic signal mast-arm infrastructure at three major intersections: Salford Boulevard, Cranberry Boulevard, Chamberlain Boulevard
  • All traffic signals including Sumter Boulevard and Toledo Blade Boulevard will be interconnected and synchronzied
  • Five miles of culvert drainage pipe
  • Twelve drainage (stormwater) detention ponds
  • Emergency traffic signal to be installed at Citizens Parkway for Fire/EMS
  • 6.3 miles of Type "F" curb and gutter
  • Approximately 14,347 tons of asphalt
  • 183 drainage curb inlets
  • 5.6 miles of 10-foot-wide concrete multi-use path
  • 21,000 landscape plants (primarily around drainage ponds)
  • LED lighted fountains at each pond
  • 246 street lights
  • Bi-directional left-turn lane (stamped concrete surface)

What will the road look like?

You can see what the initial design of the road will look like projected over the current roadway by viewing the Price Boulevard Map Projection(PDF, 9MB). Additionally, you can see what a typical section of the road will look like both on the main strip and approaching intersections by viewing the Price Boulevard Typical Section and Intersection Infographic(PDF, 490KB).

Temporary Construction Easement

Property owners on Price Boulevard will need to sign and return a Temporary Construction Easement and Right of Entry form, which gives the City temporary permission to access your property, primarily to remove and reconstruct a new driveway and do ancillary work to adjust your front yard to meet the new road and sidewalk. View an example of the Temporary Construction Easement and Right of Entry form(PDF, 130KB).

The City of North Port celebrated a groundbreaking ceremony in March 2023 to kick off the widening of Price Boulevard, a much-anticipated project that will ease congestion on this key roadway and make it more resilient in the event of future storms.

Key Features

  • Four travel lanes/two in each direction
  • A continuous bi-directional center left lane
  • A ten feet wide multi-use path on each side of the roadway

Project Features

By the Numbers:

  • Price Boulevard widening from two lanes to four lanes between Toledo Blade and Sumter boulevards
  • The project is approximately 2.8 miles in length
  • New traffic signal mast-arm infrastructure at three major intersections: Salford Boulevard, Cranberry Boulevard, Chamberlain Boulevard
  • All traffic signals including Sumter Boulevard and Toledo Blade Boulevard will be interconnected and synchronzied
  • Five miles of culvert drainage pipe
  • Twelve drainage (stormwater) detention ponds
  • Emergency traffic signal to be installed at Citizens Parkway for Fire/EMS
  • 6.3 miles of Type "F" curb and gutter
  • Approximately 14,347 tons of asphalt
  • 183 drainage curb inlets
  • 5.6 miles of 10-foot-wide concrete multi-use path
  • 21,000 landscape plants (primarily around drainage ponds)
  • LED lighted fountains at each pond
  • 246 street lights
  • Bi-directional left-turn lane (stamped concrete surface)

What will the road look like?

You can see what the initial design of the road will look like projected over the current roadway by viewing the Price Boulevard Map Projection(PDF, 9MB). Additionally, you can see what a typical section of the road will look like both on the main strip and approaching intersections by viewing the Price Boulevard Typical Section and Intersection Infographic(PDF, 490KB).

Temporary Construction Easement

Property owners on Price Boulevard will need to sign and return a Temporary Construction Easement and Right of Entry form, which gives the City temporary permission to access your property, primarily to remove and reconstruct a new driveway and do ancillary work to adjust your front yard to meet the new road and sidewalk. View an example of the Temporary Construction Easement and Right of Entry form(PDF, 130KB).

  • March 19, 2024

    Share March 19, 2024 on Facebook Share March 19, 2024 on Twitter Share March 19, 2024 on Linkedin Email March 19, 2024 link
    • Construction, Engineering and Inspection firm AECOM contract was approved by the Commission on February 27, 2024.
    • Final plans are nearing completion and the Department of Public Works anticipates advertising a solicitation for a contractor in June 2024.
    • Commission consideration of the construction contract in September/October 2024.
    • Construction work on Price Boulevard Widening, Phase I from Sumter to Toledo Blade expected to begin Fall 2024.
  • April 30, 2023

    Share April 30, 2023 on Facebook Share April 30, 2023 on Twitter Share April 30, 2023 on Linkedin Email April 30, 2023 link
    • 60% refreshed plans due to City on August 3, 2023. Refresh Design completion February 2024. Temporary Construction Easement forms have been sent out.
  • February 28, 2023

    Share February 28, 2023 on Facebook Share February 28, 2023 on Twitter Share February 28, 2023 on Linkedin Email February 28, 2023 link
    • Public Meeting was held for March 15, 2023. 60% refreshed plans are due to City on August 3, 2023.
  • January 31, 2023

    Share January 31, 2023 on Facebook Share January 31, 2023 on Twitter Share January 31, 2023 on Linkedin Email January 31, 2023 link
    • Kickoff meeting with consultant scheduled for February 10, 2023.